Here is an update on our #bike path connector #construction in south #Ottawa as of 1100 hrs this morning. The asphalt crew are about 50 feet from finishing the connection on the north side, although it looks like they will have to go over to the south side and put down about 30 ft of asphalt there to replace some removed yesterday. When that was originally laid down it was done wrong and resulted in water accumulation.